Tools that need to be prepared before installation of wear-resistant lining bricks
Installation of wear-resistant Alumina lining bricks
1. Install the ball mill on the base as soon as possible. After the cement is hardened, the ball mill can run smoothly after debugging.
2. Before installing the ball mill prepare a clean plastic bucket for mixing cement slurry and adjusting glue.
3. The light inside the ball mill is not good, you need to connect the electric light wire, install the electric light in the ball mill, and use it for working lighting.
4. Need to prepare an electric fan, which can aim at the grinding port and blow from the outside to the inside of the ball mill to ensure good ventilation in the ball mill.
5. Tools: Iron hammer, rubber hammer or wooden hammer, clay board, gloves.